On-site wastewater disposal systems include conventional septic systems, cesspools, and innovative/alternative systems. They are individual systems that treat small wastewater flows, usually under 10,000 gallons per day. Over 30% of homes in Massachusetts use on-site wastewater systems, as well as small businesses and institutions in unsewered areas.
Title V of the State Environmental Code, 310 CMR 15.000, protects you, your family, and your neighbors from these public health threats. MassDEP, local Boards of Health, and system owners all share the responsibility for the proper siting, construction, upgrade, and maintenance of on-site systems.

Septic systems that are not properly designed or maintained contribute pathogens and nutrients to groundwater and surface water, endangering drinking water supplies, shellfish beds, and surface water bodies.
Fees:
Percolation Test Application New Construction   $300.00 plus $250.00
consultant fee. Two separate checks. 

Percolation Test Application for Repairs             $200.00

Additional Perc Test Holes:                               $100.00 per hole

Septic System Application New Construction:    $300.00 plus $150.00 consultant fee. Two separate checks.

Septic System Application Repairs:                           $200.00

If the job includes an abandonment add an additional   $25.00

If the job includes a variance add an additional           $25.00

If abandoning a well add an additional                         $50.00

Emergency repairs/component replacements:             $100.00

Abandonments for sewer tie-ins                                $50.00
Note: For abandonments that are done in conjunction with a septic system installation, the permit and fee are figured in as part of the Septic System Application Fee.  Abandonments done as part of a sewer tie-in require their own permit
Septic System Inspections
Percolation Tests
Septic System Plans
Abandonments
All fees must be made by check or money order payable to the City of Taunton.  Please identify what the fee is for on the memo section of the check. 
A Percolation Test Application must be filled out with the appropriate fee to start the process.
For a percolation test application Click Here.
Requesting a Variance / Local Upgrade Approval
Septic plans must be stamped by the Conservation Department before being submitted to the Board of Health.
If the perc test is for new construction, the application is faxed to our consultant HML Associates and a representative will contact the engineer to witness the perc test.

If the perc is for a repair, then a member of the Board of Health will be in touch with the engineer to witness   the perc test


All requests for variances and soil logs must be submitted with the plans along with the appropriate checks payable to the City of Taunton.
Once the plans have been reviewed by our consultant, the home owner, contractor, and engineer will receive a letter either approving or requesting a revision of the plan with a list of required changes.
Title V Inspections
For a 9A form Click Here.
For a 9B form Click Here.
Any requests for reduction in the systems distance to property line must have proof of abutters notifications and must be approved by the Board of Health at the monthly Board meeting.
All variance paperwork must be submitted along with the septic system application.  There is an additional $25.00 fee charged for the septic system application
For a copy of the Title V regulations Click Here.
Before starting any work, an installer licensed by the Taunton Board of Health must come into the office and request the permit and plans for the job.  This permit and the licensed installer must be on site at all times. 

The Taunton Board of Health conducts an open hole inspection prior to the system being installed and  a final inspection once the system is in place.

The Board of Health also reviews the As-Built Plan for the septic system before issuing a Certificate of Compliance.

We recommend calling the office two days in advance to request an inspection so that we may be better able to conduct the inspections at the time requested. 
Before starting any work, an installer licensed by the City of Taunton must fill out an abandonment application.  The permit for the job cannot be given until we receive a copy of the sewer permit and the appropriate abandonment fee has been paid. 
Septic System Installers
If an abandonment is being done in conjunction with a septic system installation, then the abandonment is part of the septic system permit.
The Taunton Board of Health  witnesses all septic tank abandonments being crushed and backfilled.  

Note: We only witness abandonments that are the result of a sewer tie-in.  We do not witness those abandonments done due to an installation of a new septic system.

Fee:                 $50.00 per abandonment
Title V inspections can only be conducted by a licensed Title V Inspector.  The Department of Environmental Protection issues these licenses and you can find a list of licensed individuals by Clicking Here.
All Title V reports done in Taunton must be submitted to the Board of Health within 30 days of the inspection date for review.  A $25.00 filing fee is charged for each Title V report and must be supplied along with the report.
If a system fails a Title V inspection, the home owner is given two years to repair the system, unless the system poses a danger to public health and safety, in which case the Board of Health would require that the system be repaired in a more timely manner.
If you would like to be a septic system installer or do sewer tie-ins in Taunton, you must take a one-time exam issued by the Board of Health and score a 76% or better. After passing the exam, an installer will only need to renew his or her installers permit every year.
If you would like to set up a time to sit for the exam, please contact the Board of Health at (508) 821-1400.
Fees:             $25.00 Exam

$100.00 Yearly Permit Fee
Installers who do not get permitted by December 31st will incur a $50.00 late fee for the permit. 
Checks need to be made payable to the City of Taunton.
To download a copy of the application to become a septic system installer in Taunton Click Here.
There are local regulations on the following items related to septic systems in Taunton.  Click on each one for a copy of the regulation.
Kevin M. Duquette
Environmental Compliance Officer
Taunton Board of Health

Phone: (508) 821-1400
Fax: (508) 821-1403

or via e-mail at
Cotboh5@tmlp.net
To register a complaint, please call (508) 821-1400 so that your issue can be addressed in a timely manner.
or

Robert E. Buker
Sanitary Inspector

Phone: (508) 821-1400
Fax: (508) 821-1403

or via e-mail at
Cotboh2@tmlp.net